When a college in Oxfordshire approached our team, its sports department was facing a familiar problem. Demand for outdoor sports facilities was increasing, but the existing playing areas were struggling to accommodate the college's timetable.
The main outdoor court had deteriorated after years of regular use. Its surface was worn, the markings had faded, and drainage problems meant that sections remained wet long after rainfall.
The college also relied on natural grass areas for football and general sports activities, which became difficult to use during prolonged wet weather.
The facilities manager explained that the college wanted a more dependable outdoor space for PE sessions, student recreation and organised sports clubs.
Their priority was to improve the existing hard court rather than undertake a complete redevelopment of the sports grounds.
Following our initial assessment, we recommended reconstructing the ageing court as a modern porous macadam Multi-Use Games Area (MUGA), complete with a specialist sports coating, new fencing and multi-sport line markings.
The first meeting brought together the facilities manager, the sports department and our project supervisor.
One of the lecturers explained that the college frequently had to reorganise activities because the outdoor court was unsuitable for use after wet weather.
They asked whether a new surface would allow students to use the area throughout the year.
We explained that a properly designed porous macadam court could improve surface water management and provide a more dependable facility than the deteriorated existing court.
However, we were careful to explain that no outdoor sports surface can remain playable in every weather condition. Ice, snow, extreme rainfall and maintenance requirements can still restrict use.
The college also wanted flexibility.
The new MUGA needed to accommodate basketball, netball, tennis and general recreational activities without creating confusion between the different court layouts.
We agreed on a coloured sports surface with contrasting line markings, allowing each activity to be identified more easily.
The proposed construction programme was approximately five weeks, scheduled during the summer break to minimise disruption.
The first week was dedicated to site establishment, removal of the deteriorated playing surface and investigation of the existing base.
Our team lifted the unsuitable surfacing and removed damaged sections of the underlying construction.
Once the area was exposed, we checked the formation and confirmed the required preparation works.
Several sections needed additional attention because the existing levels had contributed to standing water.
We corrected the affected areas and prepared the site for the new pavement construction.
The college's facilities manager visited during this stage and asked why we were replacing sections beneath the visible surface.
We explained that applying a new playing surface over an unsuitable base would risk carrying the existing problems into the refurbished facility.
They agreed that it was better to address the underlying issues properly rather than focus only on the finished appearance.
During the second week, we progressed with the drainage and sub-base works.
The new construction was designed to allow water to pass through the porous playing surface and into the specified drainage arrangement.
Our operatives installed and compacted the required aggregate layers, checking levels and falls throughout the process.
Once the base was ready, we began installing the porous sports macadam.
The macadam was laid and compacted in accordance with the agreed specification to create a consistent playing surface.
This stage continued into the third week, allowing time for the required inspections and preparation for the coating system.
We also coordinated the perimeter fencing works, replacing damaged sections and installing new access gates where required.
The fourth week focused on the finishing stages.
Once the macadam was suitable for coating, our team applied the specified sports surface coating in accordance with the manufacturer's requirements.
The college selected a blue playing area with a green perimeter, creating a clear visual distinction between the main court and the surrounding space.
We then set out the individual court layouts.
Basketball, netball and tennis markings were applied in contrasting colours to help students and staff identify the appropriate boundaries.
Our installers checked the measurements carefully before applying the specialist line marking paint.
The sports department visited again as the markings were being completed.
One lecturer commented that the clearer layout would make it easier to organise lessons involving different activities, particularly when students were rotating between sports.
It was encouraging to hear that the design choices made during our initial meetings were already proving useful.
The fifth week was allocated to completing the remaining details and preparing the court for use.
We checked the surface finish, inspected the fencing and gates, reviewed the court markings and completed the agreed quality checks.
We also made sure the coating had received the required curing time before the area was reopened.
At handover, we provided the college with guidance on routine maintenance.
For a porous macadam sports court, this includes regular removal of leaves and debris, suitable cleaning to reduce the risk of blocked surface voids, and periodic inspections for wear or damage.
We also recommended monitoring the court's drainage performance and arranging specialist maintenance when required.
The completed project provided the college with a reconstructed outdoor MUGA designed for regular educational and recreational use.
The new porous construction addressed the limitations of the deteriorated court, while the coloured coating and clearly defined markings made the space more practical for different sports.
The fencing improvements also helped create a more clearly enclosed playing area.
The main works were completed over approximately five weeks, within the planned summer construction period.
For the college, the most important improvement was having a dedicated outdoor sports facility that could support a wider range of activities and offer better surface water management than the previous court.
For our team, the project demonstrated how investing in the underlying construction can be just as important as choosing the right finished sports surface.
We help colleges, schools, universities, sports clubs and leisure organisations explore sports court construction, MUGA resurfacing, drainage improvements and refurbishment projects across the UK.
Whether you need to replace an ageing outdoor court or develop a new multi-sport facility, our team can discuss suitable surface specifications, construction programmes and maintenance requirements.
Contact us today to request a quotation and find out how we can help improve your outdoor sports facilities.